| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AUXCIMACOL | Cimbra aparente en Columnas. Incluye: cimbrado y descimbrado con madera y triplay, materiales, mano de obra, equipo, herramienta. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MACMD1X4X81/4 | Duela 1" x4"x8 1/4' | pt | 0.200000 | $5.44 | $1.09 |
| MACMBRR2X4X8.25 | Barrote 2"x4"x8 1/4' | pt | 2.370000 | $5.06 | $11.99 |
| MACMPL4X4X81/4 | Polin de 4" x 4" regular | pt | 1.180000 | $5.06 | $5.97 |
| MACMCHL1X8 | Chaflan de 1" x 8' | m | 2.200000 | $1.37 | $3.01 |
| A4EAR020 | Clavo c/cabeza de 2"-4" | kg | 0.090910 | $13.91 | $1.26 |
| A4BAR013 | Alambre recocido Calibre 16 | kg | 0.058820 | $11.35 | $0.67 |
| SEPAROL | Separol, desmoldante para cimbras | Lt | 0.125000 | $16.96 | $2.12 |
| MACMTRPL16MM | Triplay de 1.22x2.44m 16 mm 1c (pieza) | hoja | 0.092380 | $254.00 | $23.46 |
| Suma de Material | $49.57 | ||||
| Mano de Obra | |||||
| JOGP023 | Cuadrilla de 1 cimbrador + 1 ayudante + cabo | Jor | 0.117650 | $481.29 | $56.62 |
| Suma de Mano de Obra | $56.62 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.030000 | $56.62 | $1.70 |
| Suma de Herramienta | $1.70 | ||||
| Otros | |||||
| AND004 | Andamio de 4.00 m. de altura, construido con una torre de trabajo de tubo de acero, con ruedas y base de tablones de madera. | r/d | 0.117650 | $18.59 | $2.19 |
| Suma de Otros | $2.19 | ||||
| Costo Directo | $110.08 |