| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ANDAMIO EN COLUMNAS | andamio estructural en columnas | r/dia |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ANDAMIO-03 | MARCO METALIC0 | PZA | 6.000000 | $1.45 | $8.70 |
| ESCALERA PARA AND | ESCALERA PARA ANDAMIO | R/D | 4.000000 | $1.00 | $4.00 |
| ANDAMIO-02 | TIJERAS AND. ATLAS | PZA | 8.000000 | $0.81 | $6.48 |
| ANDAMIO-04 | COPLE PARA ANDAMIO | PZA | 6.000000 | $0.22 | $1.32 |
| CRUCETA | CRUCETA PARA ANDAMIO | PZA | 2.000000 | $0.48 | $0.96 |
| ANDAMIO-01 | PLATAFORMA METALICA | PZA | 2.000000 | $4.93 | $9.86 |
| BARANDAL | BARANDAL PARA ANDAMIO | R/D | 1.000000 | $0.43 | $0.43 |
| RUEDAS DE HULE | ruedas de hule | pza | 4.000000 | $1.25 | $5.00 |
| Suma de Material | $36.75 | ||||
| Mano de Obra | |||||
| CUAD OC 02 | CUAD. 2 (1 ALBAñIL + 1 PEON) | JOR | 0.039302 | $876.36 | $34.44 |
| Suma de Mano de Obra | $34.44 | ||||
| Costo Directo | $71.19 |