| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BASICO150 | CONCRETO HIDRAULICO DE F'c=150Kg/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-06 | cemento gris | ton | 0.360000 | $1,586.20 | $571.03 |
| MAT20 | GRAVA LIMPIA PARA CONCRETO INCLUYE ACARREO | M3 | 0.700000 | $161.81 | $113.27 |
| MAT21 | ARENA INCLUYE ACARREO | M3 | 0.480000 | $146.85 | $70.49 |
| Suma de Material | $754.79 | ||||
| Equipo | |||||
| EQ0012 | REVOLVEDORA MIPSA DE 1 SACO DE 8 HP MOT.KHOLER | hora | 0.300000 | $78.70 | $23.61 |
| Suma de Equipo | $23.61 | ||||
| Otros | |||||
| BASICOALBAÑIL | CUADRILLA DE ALBAÑIL | JOR | 0.050000 | $1,170.90 | $58.55 |
| BASAGUA | AGUA | M3 | 0.240000 | $14.30 | $3.43 |
| Suma de Otros | $61.98 | ||||
| Costo Directo | $840.38 |