| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTOGRIS | Cemento Portland ordinario color gris | ton | 0.326000 | $1,617.20 | $527.21 |
| ARENA | ARENA | m3 | 0.536000 | $157.63 | $84.49 |
| GRAVA-ARENA | GRAVA -ARENA | m3 | 0.650000 | $160.00 | $104.00 |
| AGUA | AGUA | M3 | 0.263000 | $40.00 | $10.52 |
| Suma de Material | $726.22 | ||||
| Mano de Obra | |||||
| CUA OP EQUIPO 7 | CUAD. 1 OP. DE EQUIPO + 7 PEONES | jor | 0.083330 | $2,522.06 | $210.16 |
| Suma de Mano de Obra | $210.16 | ||||
| Equipo | |||||
| AREVOLVEDORA | REVOLVEDORA 8 H.P | hora | 0.670000 | $71.23 | $47.72 |
| Suma de Equipo | $47.72 | ||||
| Costo Directo | $984.10 |