| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA EN LOSAS | CIMBRA EN LOSAS | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIAMP110 | cimbra imp 1.22x2.44m 16mm 1c | M2 | 0.250000 | $92.14 | $23.04 |
| CIAMP090 | polin de 3 1/2"x3 1/2" regular | PT | 1.800000 | $9.80 | $17.64 |
| CIAMP035 | barrote 1 1/2" x 4" x 8' | PT | 1.250000 | $5.62 | $7.03 |
| CIAMP045 | chaflan de 3/4" x 8' | ML | 0.550000 | $2.00 | $1.10 |
| CIAMP055 | duela 3/4" x 4" x 8' | PT | 0.750000 | $7.52 | $5.64 |
| CIMBRA-02 | CLAVO | Kg. | 0.280000 | $17.10 | $4.79 |
| DIESEL | DESMOLDANTE | Lt | 0.500000 | $6.10 | $3.05 |
| Suma de Material | $62.29 | ||||
| Mano de Obra | |||||
| CUA CARPINTERO 2 | (1 Oficial carpintero de obra negra + 1 ayte.) | JOR | 0.100000 | $733.32 | $73.33 |
| Suma de Mano de Obra | $73.33 | ||||
| Costo Directo | $135.62 |