| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MUROBLOCK20 | Muro block hueco 20x20x40 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ESCALERILLA | REFUERZO PARA MURO DE BLOCK | ML | 2.600000 | $7.00 | $18.20 |
| ACERO REF NO.4 | Acero de refuerzo # 4 | KG | 1.100000 | $8.33 | $9.16 |
| BLCOCK CONCR.20X2040 | BLOCK HUECO DE CONCRETO 20X20X40 CM. | PZA | 13.750000 | $7.00 | $96.25 |
| DISCO DE DIAMANTE | DISCO DE DIAMANTE | PZA | 0.000500 | $1,460.72 | $0.73 |
| AGREGADO-003 | AGUA ACARREO INTERNO | M3 | 0.010000 | $40.00 | $0.40 |
| Suma de Material | $124.74 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.180000 | $633.72 | $114.07 |
| Suma de Mano de Obra | $114.07 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | Andamio metalico | (%)mo | 0.040000 | $114.07 | $4.56 |
| Suma de Herramienta | $4.56 | ||||
| Otros | |||||
| MORTERO 1:5 | MORTERO CEMENTO ARENA 1:5 | M3 | 0.010000 | $839.87 | $8.40 |
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3. | 0.013000 | $983.37 | $12.78 |
| Suma de Otros | $21.18 | ||||
| Costo Directo | $264.55 |