| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO FC 150 H/O | CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, T.M.A. 40 MM., HECHO EN OBRA CON REVOLVEDORA, INCLUYE: ACARREOS A 20 MTS. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS | CEMENTO GRIS | TON | 0.314200 | $1,269.56 | $398.90 |
| ARENA | ARENA LIMPIA DE BANCO | M3 | 0.463300 | $28.50 | $13.20 |
| GRAVA 3/4" | GRAVILLA DE 3/4" | M3 | 0.741500 | $180.00 | $133.47 |
| AGUA | ACARREO INTERNO | M3 | 0.241200 | $6.50 | $1.57 |
| Suma de Material | $547.14 | ||||
| Mano de Obra | |||||
| CUADRILLA NO.99 | CUADRILLA DE PEONES : 5 PEONES | JOR | 0.066700 | $1,276.52 | $85.14 |
| Suma de Mano de Obra | $85.14 | ||||
| Equipo | |||||
| REVOLVEDORA 8 H.P. | REVOLVEDORA DE 8 H.P. | HORA | 0.533300 | $46.22 | $24.65 |
| Suma de Equipo | $24.65 | ||||
| Costo Directo | $656.93 |