| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO FC=100 | CONCRETO DE F´C=100 KG/CM2 | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ARENA | ARENA DE BANCO | m3 | 0.544600 | $160.00 | $87.14 |
| CEMENTO CPO-30RS | CEMENTO TIPO CPO-30RS, PORTLAND TIPO II MCA. MAYA | ton | 0.275000 | $2,200.00 | $605.00 |
| GRAVA | GRAVA DE 3/4" | M3 | 0.659100 | $260.00 | $171.37 |
| Suma de Material | $863.51 | ||||
| Mano de Obra | |||||
| CUAD.ELABORACION CO | CUADRILLA PARA ELABORACION DE MEZCLAS Y CONCRETOS | JOR | 0.090909 | $2,600.78 | $236.44 |
| Suma de Mano de Obra | $236.44 | ||||
| Herramienta | |||||
| D-HERRAMIENTA MENOR | HERRAMIENTA MENOR | (%)mo | 0.030000 | $236.44 | $7.09 |
| D-HERRAMIENTA MENOR | HERRAMIENTA MENOR | (%)mo | 0.030000 | $236.44 | $7.09 |
| Suma de Herramienta | $14.18 | ||||
| Equipo | |||||
| REVOL 1 SACO | REVOLVEDORA 1 SACO MCA MIPSA KHOLER DE 8 H.P. | HORA | 0.557000 | $29.22 | $16.28 |
| Suma de Equipo | $16.28 | ||||
| Costo Directo | $1,130.41 |