| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ANDAMIO | ANDAMIO metalicos | DIA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ANDAMIO-03 | MARCO METALIC0 155-0 | PZA-- | 2.000000 | $1.31 | $2.62 |
| ANDAMIO-02 | CRUCETA O TIJERAS AND. ATLAS 255-07 | PZA-- | 2.000000 | $0.48 | $0.96 |
| ANDAMIO-04 | COPLE PARA ANDAMIO | PZA-- | 2.000000 | $0.22 | $0.44 |
| ANDAMIO-01 | PLATAFORMA METALICA 2.13 MTS TD/S-7 | PZA-- | 0.020000 | $5.94 | $0.12 |
| Suma de Material | $4.14 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.025000 | $645.21 | $16.13 |
| Suma de Mano de Obra | $16.13 | ||||
| Costo Directo | $20.27 |