| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA ESTRUCTURA | CIMBRA COMÚN EN ESTRUCTURA COLUMNAS, TRABES, MUROS Y LOSAS CUALQUIER ALTURA Y/O NIVEL INCLUYE: CIMBRADO, DESCIMBRADO, CURADO, SUMINISTRO, MATERIALES DE CONSUMO, MANO DE OBRA Y TRABAJOS NECESARIOS. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA-04 | MADERA DE PINO | PT-- | 5.020000 | $5.60 | $28.11 |
| CIMBRA-02 | CLAVO | Kg.-- | 0.090000 | $13.54 | $1.22 |
| CIMBRA-01 | CIMBRAPLAY 16 MM | M2** | 0.170000 | $80.62 | $13.71 |
| ACERO-18 | ALAMBRE RECOCIDO | KG-- | 0.050000 | $12.17 | $0.61 |
| COMBUSTIBLE 01 | DIESEL | LT | 0.500000 | $4.68 | $2.34 |
| Suma de Material | $45.99 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | JOR | 0.146400 | $568.08 | $83.17 |
| Suma de Mano de Obra | $83.17 | ||||
| Costo Directo | $129.16 |