| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TERMOLITA 1 | TERMOCRET | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TERMOCRET 1 | TERMOLITA INC ADITIVO Y MEMBRANA DE REF | BULTO | 10.000000 | $82.00 | $820.00 |
| CEMENTO GRIS 1 | CEMENTO GRIS NORMAL | TON | 0.250000 | $2,378.40 | $594.60 |
| AGUA ADQUIRIDA 1 | AGUA ADQUIRIDA | M3 | 0.400000 | $31.50 | $12.60 |
| Suma de Material | $1,427.20 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.015000 | $290.45 | $4.36 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.150000 | $233.90 | $35.09 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.500000 | $169.01 | $84.51 |
| Suma de Mano de Obra | $123.96 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $123.96 | $3.72 |
| Suma de Herramienta | $3.72 | ||||
| Costo Directo | $1,554.88 |