| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CON-350 | CONCRETO HECHO EN OBRA F'C=350 KG/CM2 RESISTENCIA NORMAL AGREGADO MAXIMO 3/4" | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| M-0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.489000 | $2,325.96 | $1,137.39 |
| M-0302-20 | ARENA | M3 | 0.548000 | $237.51 | $130.16 |
| M-0302-30 | GRAVA | M3 | 0.686000 | $179.46 | $123.11 |
| M-0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.263000 | $14.95 | $3.93 |
| Suma de Material | $1,394.59 | ||||
| Mano de Obra | |||||
| CUA-103 | cuadrilla no. 103 | jor | 0.066600 | $1,355.04 | $90.25 |
| Suma de Mano de Obra | $90.25 | ||||
| Equipo | |||||
| EQ-4050 | REVOLVEDORA | hora | 0.533300 | $20.39 | $10.87 |
| Suma de Equipo | $10.87 | ||||
| Costo Directo | $1,495.71 |