| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 03-2070 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MÁXIMO 3/4" | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.370000 | $1,826.00 | $675.62 |
| 0302-20 | ARENA | M3 | 0.600000 | $160.00 | $96.00 |
| 0302-30 | GRAVA | M3 | 0.700000 | $250.00 | $175.00 |
| 0302-05 | AGUA EN PIPA | M3 | 0.260000 | $60.00 | $15.60 |
| Suma de Material | $962.22 | ||||
| Mano de Obra | |||||
| 02-1030 | CUADRILLA No 103 (FABRICACION DE CONCRETO CON REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.125000 | $2,153.83 | $269.23 |
| Suma de Mano de Obra | $269.23 | ||||
| Equipo | |||||
| 03-4050 | REVOLVEDORA PARA CONCRETO MIPSA-KOHLER R-10 8 H.P. 1 SACO | Hora | 1.000000 | $26.13 | $26.13 |
| Suma de Equipo | $26.13 | ||||
| Costo Directo | $1,257.58 |