| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ANDAMIO | ANDAMIO RENTA POR mes | DIA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ANDAMIO-03 | MARCO METALIC0 | PZA | 4.000000 | $1.72 | $6.88 |
| ANDAMIO-02 | TIJERAS AND. ATLAS | PZA | 4.000000 | $0.58 | $2.32 |
| ANDAMIO-04 | COPLE PARA ANDAMIO | PZA | 8.000000 | $0.27 | $2.16 |
| CRUCETA | CRUCETA PARA ANDAMIO | PZA | 4.000000 | $0.48 | $1.92 |
| ANDAMIO-01 | PLATAFORMA METALICA | PZA | 3.000000 | $6.75 | $20.25 |
| BARANDAL | BARANDAL | PZA | 2.000000 | $0.51 | $1.02 |
| RUEDAS DE HULE | ruedas de hule | pza | 4.000000 | $2.19 | $8.76 |
| 03-7020 | POSTE PARA BARANDAL | R/D | 2.000000 | $0.51 | $1.02 |
| Suma de Material | $44.33 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | jor | 0.050000 | $979.14 | $48.96 |
| Suma de Mano de Obra | $48.96 | ||||
| Costo Directo | $93.29 |