| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA APA EST | Suministro y colocacion de cimbra acabado aparente en estructura principal, (columnas y trabes) | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 2.960000 | $5.61 | $16.61 |
| MADERA POLIN | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 4.920000 | $6.50 | $31.98 |
| MADERA-6 | CIMBRAPLAY 16 MM HOJA DE 1.22 X 2.44 | M2 | 0.250000 | $92.00 | $23.00 |
| MADERA CHAFLAN | CHAFLAN 1" | Ml | 1.900000 | $3.20 | $6.08 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.250000 | $17.00 | $4.25 |
| ALAMBRE | ALAMBRE RECOCIDO. | KG | 0.233000 | $14.87 | $3.46 |
| ACERO NO. 2 | Acero de refuerzo núm. 2 (1/4" ) fyp = 2530 kg/ml | KG | 0.233000 | $13.45 | $3.13 |
| DIESEL | DIESEL | LTS | 0.600000 | $6.50 | $3.90 |
| Suma de Material | $92.41 | ||||
| Mano de Obra | |||||
| CUA CARPINTERO 2 | (1 Oficial carpintero de obra negra + 1 ayte.) | JOR | 0.104712 | $803.53 | $84.14 |
| Suma de Mano de Obra | $84.14 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR | herramienta menor | (%)mo | 0.030000 | $84.14 | $2.52 |
| EQUIPO DE SEGURIDAD | Equipo de Primera Seguridad (Casco, Botas, Guantes, Gafas, Chaleco Preventivo) | (%)mo | 0.030000 | $84.14 | $2.52 |
| ANDAMIOS | ANDAMIOS | (%)mo | 0.030000 | $84.14 | $2.52 |
| Suma de Herramienta | $7.56 | ||||
| Costo Directo | $184.11 |