| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 03-2050 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL , AGREGADO MAXIMO 11/2" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.326000 | $1,565.00 | $510.19 |
| 0302-20 | ARENA | M3 | 0.536000 | $80.00 | $42.88 |
| 0302-30 | GRAVA | M3 | 0.650000 | $120.00 | $78.00 |
| 0302-05 | AGUA DE ACARREO | M3 | 0.263000 | $34.88 | $9.17 |
| 0173-55 | FESTERMIX R.R. | CUB | 0.333600 | $169.00 | $56.38 |
| Suma de Material | $696.62 | ||||
| Mano de Obra | |||||
| 02-1030 | CUADRILLA No 103 ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.066670 | $2,456.26 | $163.76 |
| Suma de Mano de Obra | $163.76 | ||||
| Equipo | |||||
| 03-4050 | REVOLVEDORA PARA CONCRETO MIPSA-KOHLER R-10 8 H.P. 1 SACO | Hora | 0.533300 | $28.98 | $15.46 |
| Suma de Equipo | $15.46 | ||||
| Costo Directo | $875.84 |