| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AUX-1 | CONCRETO f'c= 150 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ALB006 | CEMENTO PORTLAND NORMAL CPO 30RS EN SACO DE 50 KG MARCA APASCO | TON | 0.368000 | $2,200.00 | $809.60 |
| ALB003 | ARENA DE LA REGION | M3 | 0.531000 | $320.00 | $169.92 |
| ALB004 | GRAVA CLASIFICADA LIBRE DE IMPUREZAS DE 3/4" DE DIAMETRO. | M3 | 0.643000 | $240.00 | $154.32 |
| ALB002 | AGUA PUESTA EN SITIO | M3 | 0.252000 | $18.24 | $4.60 |
| Suma de Material | $1,138.44 | ||||
| Mano de Obra | |||||
| CUA08 | CUADRILLA 1 ALBAÑIL + 5 AYUDANTES | JOR | 0.250000 | $2,441.53 | $610.38 |
| Suma de Mano de Obra | $610.38 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.025000 | $610.38 | $15.26 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.025000 | $610.38 | $15.26 |
| Suma de Herramienta | $30.52 | ||||
| Equipo | |||||
| AME-26 | REVOLVEDORA PARA CONCRETO MARCA CIPSA MODELO R10 DE UN SACO TIPO TROMPO, CAP. 5 M3/HR, MOTOR A GASOLINA MARCA KOHLER DE 8 HP, CON REDUCTOR, MONTADA SOBRE RUEDAS TIPO B78X-13, PESO DE LA MÁQUINA CON MOTOR 363 KG. | HORA | 0.500000 | $70.75 | $35.38 |
| AME-43 | VIBRADOR PARA CONCRETO MARCA DYNAPAC-KOHLER MODELO K-91 DE 4 H.P. LONGITUD 14 PIES | HORA | 0.500000 | $68.04 | $34.02 |
| AME-37 | CAMION CAPACIDAD DE 4 TON., MARCA FORD, F-350, MODELO 2008. | HORA | 0.005000 | $202.74 | $1.01 |
| Suma de Equipo | $70.41 | ||||
| Otros | |||||
| CURF01 | SUMINISTRO Y APLICACION DE CURADO CURAFEST | M2 | 3.000000 | $38.06 | $114.18 |
| PBA96 | SUMINISTRO DE PERSONAL Y EQUIPO PARA PRUEBA DE REVENIMIENTO Y RESISTENCIA A LA COMPRESION A CONCRETO | JOR | 0.020000 | $2,873.87 | $57.48 |
| Suma de Otros | $171.66 | ||||
| Costo Directo | $2,021.41 |