| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 03-2020 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.273000 | $1,500.00 | $409.50 |
| 0302-20 | ARENA | M3 | 0.542000 | $35.00 | $18.97 |
| 0302-30 | GRAVA | M3 | 0.656000 | $185.00 | $121.36 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.271000 | $50.00 | $13.55 |
| Suma de Material | $563.38 | ||||
| Mano de Obra | |||||
| VERMEX NO 04 | CUADRILLA No 103 ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.066600 | $1,230.24 | $81.93 |
| Suma de Mano de Obra | $81.93 | ||||
| Equipo | |||||
| 03-4050 | REVOLVEDORA PARA CONCRETO MIPSA-KOHLER R-10 8 H.P. 1 SACO | Hora | 0.533300 | $23.52 | $12.54 |
| Suma de Equipo | $12.54 | ||||
| Costo Directo | $657.85 |