| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRA EN CIMENTACIO | CIMBRA PARA CIMENTACION | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRIPLAY 19MMPINO 1A | CIMBRAPLAY DE 19 MM EN PINO DE PRIMERA UNA CARA | M2 | 0.167000 | $80.00 | $13.36 |
| M-BARROTE2X4X8PINO3A | BARROTE DE 2" X 4" X 8' PINO DE 3A | PT | 0.200000 | $7.00 | $1.40 |
| M-POLIN 4X4 PINO 3A | POLIN DE 4" X 4" PINO DE 3A | PT | 0.400000 | $7.00 | $2.80 |
| M-DUELA1X4" PINO 3A | DUELA DE 1" X 4" PINO DE 3A | PT | 0.400000 | $7.00 | $2.80 |
| M-CHAFLAN 1" PINO3A | CHAFLAN DE 1" PINO DE 3A | ML | 0.250000 | $2.55 | $0.64 |
| CLAVO DE 2 1/2" A 3 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.400000 | $12.00 | $4.80 |
| DIESEL | DIESEL | LT | 0.400000 | $6.20 | $2.48 |
| Suma de Material | $28.28 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 03 | CUADRILLA NO. 3 (1 CARPINTERO DE OBRA NEGRA + 1 AYTE. "B") | JOR | 0.017090 | $656.02 | $11.21 |
| CUADRILLA NO. 03 | CUADRILLA NO. 3 (1 CARPINTERO DE OBRA NEGRA + 1 AYTE. "B") | JOR | 0.040000 | $656.02 | $26.24 |
| Suma de Mano de Obra | $37.45 | ||||
| Costo Directo | $65.73 |