| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| POZO DE VISITA | POZO DE VISITA | pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TAB7-14 | TABIQUE ROJO RECOCIDO | PZA | 850.000000 | $1.50 | $1,275.00 |
| AGUA | AGUA | M3 | 1.750000 | $30.00 | $52.50 |
| TEPETATE | TEPETATE | M3 | 11.500000 | $65.00 | $747.50 |
| ESCALONES P/PV | ESCALONES PARA POZO DE VISITA | pieza | 7.000000 | $175.00 | $1,225.00 |
| Suma de Material | $3,300.00 | ||||
| Mano de Obra | |||||
| 03 ALB+PEON | CUADRILLA OFIC ALB+PEON | jor | 2.250000 | $606.94 | $1,365.62 |
| CUADRILLA 02 PEON | PEON | jor | 0.750000 | $271.11 | $203.33 |
| Suma de Mano de Obra | $1,568.95 | ||||
| Equipo | |||||
| RETRO | RETROEXCAVADORA CON CARGADOR | Hora | 1.000000 | $283.49 | $283.49 |
| PLACA | PLACA VIBRATORIA MANUAL DYNAPAC DE 8.00 HP. | Hora | 3.000000 | $59.05 | $177.15 |
| CAMION VOLTEO | CAMION DE VOLTEO FORD 6m3. | Hora | 0.750000 | $235.43 | $176.57 |
| Suma de Equipo | $637.21 | ||||
| Otros | |||||
| MOR1-3 | MORTERO CEMENTO-ARENA 1:3 | M3 | 0.750000 | $905.04 | $678.78 |
| CONCRETO 150 19MM | CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4 HECHO EN OBRA" | M3 | 0.870000 | $674.55 | $586.86 |
| MORTERO 1:1:4 | MORTERO CEMENTO CAL ARENA PROPORCION 1:1:4 | M3 | 0.250000 | $518.90 | $129.73 |
| Suma de Otros | $1,395.37 | ||||
| Costo Directo | $6,901.53 |