| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BASICO100 | CONCRETO HIDRAULICO DE F'c=100 KG/CM2 SIMPLE | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAT19 | CEMENTO PORTLAND | TON | 0.325000 | $1,850.00 | $601.25 |
| MAT20 | GRAVA LIMPIA PARA CONCRETO INCLUYE ACARREO | M3 | 0.692000 | $145.00 | $100.34 |
| MAT21 | ARENA INCLUYE ACARREO | M3 | 0.517000 | $68.00 | $35.16 |
| MAT05 | AGUA | M3 | 0.224000 | $22.00 | $4.93 |
| Suma de Material | $741.68 | ||||
| Equipo | |||||
| EQ0004 | PIPA DE AGUA DE 10,000LTS S/CHASIS MCA.DODGE DE 130 HP | hora | 0.001000 | $209.95 | $0.21 |
| EQ0012 | REVOLVEDORA MIPSA DE 1 SACO DE 8 HP MOT.KHOLER | hora | 0.400000 | $79.06 | $31.62 |
| Suma de Equipo | $31.83 | ||||
| Otros | |||||
| BASICOALBAÑIL | CUADRILLA DE ALBAÑIL | JOR | 0.125000 | $996.19 | $124.52 |
| Suma de Otros | $124.52 | ||||
| Costo Directo | $898.03 |