| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONC. F-C=200KG/CM2. | CONCRETO HECHO EN OBRA F'C=200 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONS006 | CEMENTO GRIS PORTLAND | TON | 0.368000 | $1,671.17 | $614.99 |
| FESTEGRAL | IMPERMEABILIZANTE INTEGRAL FESTEGRAL DE LA MARCA FESTER | KG | 14.720000 | $23.83 | $350.78 |
| CONS002 | ARENA DE LA REGION | M3 | 0.531000 | $257.00 | $136.47 |
| GRAVA | GRAVA | M3 | 0.643000 | $291.23 | $187.26 |
| CONS001 | AGUA PUESTA EN OBRA EN PIPA | M3 | 0.252000 | $19.77 | $4.98 |
| Suma de Material | $1,294.48 | ||||
| Mano de Obra | |||||
| CUAD031 | CUADRILLA PARA ELABORACION DE CONCRETO | jor | 0.066667 | $2,071.08 | $138.08 |
| Suma de Mano de Obra | $138.08 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $138.08 | $5.52 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $138.08 | $2.76 |
| Suma de Herramienta | $8.28 | ||||
| Otros | |||||
| MAQ016 | EQUIPO REVOLVEDORA | hora | 0.666700 | $19.24 | $12.83 |
| Suma de Otros | $12.83 | ||||
| Costo Directo | $1,453.67 |