| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO 250 PILOTES | CONCRETO 250 KG/CM2 EN PILOTES | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA EN PIPA | AGUA PUESTA EN OBRA ACARREADA EN PIPA. | M3 | 0.060000 | $50.00 | $3.00 |
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2, ELABORADO CON CEMENTO RESISTENTE A LOS SULFATOS Y ALCALISIS | M3 | 1.050000 | $1,125.00 | $1,181.25 |
| Suma de Material | $1,184.25 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.067500 | $1,642.77 | $110.89 |
| CUADRILLA CARO. ON | (1 Of. Carpintero O.N. + 1Ayte). | JOR | 0.166700 | $759.03 | $126.53 |
| Suma de Mano de Obra | $237.42 | ||||
| Otros | |||||
| CIMBRA METALICA COLU | CIMBRA METALICA EN COLUMNAS Y OTROS ELEMENTOS | PZA | 0.004000 | $28,553.85 | $114.22 |
| Suma de Otros | $114.22 | ||||
| Costo Directo | $1,535.89 |