| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONLOS 200KG/CM2 | CONCLOS 200KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.380000 | $1,565.00 | $594.70 |
| Suma de Material | $594.70 | ||||
| Mano de Obra | |||||
| 1ALBAÑIL+6AYUD | 1ALBAÑIL+6AYUDANTES+1/10 CABO | jor | 0.100000 | $2,244.53 | $224.45 |
| Suma de Mano de Obra | $224.45 | ||||
| Equipo | |||||
| REVOLVEDORA 1S | REVOLVEDORA DE 1 SACO MOTOR KHOLER 8 HP | HR | 0.450000 | $10.47 | $4.71 |
| VIBRADOR DE CHICOTE | VIBRADOR DE CHICOTE | HR | 0.025000 | $58.06 | $1.45 |
| CAMION PIPA 1OOOOLTS | CAMION PIPA DE 10000 LTS | HR | 0.025000 | $261.84 | $6.55 |
| Suma de Equipo | $12.71 | ||||
| Otros | |||||
| GRAVA DE BANCO | GRAVA DE BANCO | M3 | 0.680000 | $79.53 | $54.08 |
| AGUA INCLUYE ACARR | AGUA INCLUYE ACARREO | M3 | 0.260000 | $51.08 | $13.28 |
| ARENA DE BANCO | ARENA DE BANCO | M3 | 0.580000 | $74.68 | $43.31 |
| Suma de Otros | $110.67 | ||||
| Costo Directo | $942.53 |