| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EDIF-ANDAMIOS | ANDAMIAJE PARA APUNTALAMIENTO DE TRABES PREFABRICADAS Y CIMBRA EN VOLADOS. | DIA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PIE DERECHO | DIA DE RENTA POR PIE DERECHO MOD. 702-0 PARA APUNTALAMIENTO | DIA | 48.000000 | $1.69 | $81.12 |
| BASE TORNILLO | TORNILLO C/BASE MODELO 340-0 | pza | 104.000000 | $1.54 | $160.16 |
| VIGA A. R. | VIGA A.R. DE 2.44 MTS MOD. 6220-08 | DIA | 52.000000 | $1.84 | $95.68 |
| VIGA A.R. 3.05 MTS | VIGA ALTA RESISTENCIA DE 3.05 MTS MOD 6220-10 | DIA | 12.000000 | $2.33 | $27.96 |
| ANDAMIOS-ATLAS-04 | TORNILLO CON CABEZAL MOD. 353-0 | pza | 104.000000 | $1.54 | $160.16 |
| VIGA EXTENSIBLE | VIGA EXTENSIBLE MOD. QB III | DIA | 20.000000 | $3.79 | $75.80 |
| ANDAMIOS-ATLAS-03 | CRUCETA MOD 555-12 | pza | 56.000000 | $0.75 | $42.00 |
| COPLES-01 | COPLE MOD. 400-0 | DIA | 104.000000 | $0.29 | $30.16 |
| PERNO AJUSTE | PERNO AJUSTE MOD. 406-0 | DIA | 104.000000 | $0.42 | $43.68 |
| ANDAMIOS-ATLAS-01 | MARCO EXTENSIBLE MOD. 156-6 | pza | 56.000000 | $1.87 | $104.72 |
| Suma de Material | $821.44 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 02 | (2 peones). | jor | 1.000000 | $836.72 | $836.72 |
| Suma de Mano de Obra | $836.72 | ||||
| Costo Directo | $1,658.16 |