| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ANDAMIO METALIC3MTS | ANDAMIO DE 3 MTS DE ALTURA | DIA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MARCO AND. ATLAS | MARCO METALICA | PZA | 2.000000 | $2.10 | $4.20 |
| TIJERAS AND. ATLAS | TIJERAS AND. ATLAS | PZA | 2.000000 | $0.75 | $1.50 |
| COPLES AND. ATLAS | COPLES AND. ATLAS | PZA | 4.000000 | $0.32 | $1.28 |
| MADERA-5 | TABLON P/ANDAMIO | PZA | 0.050000 | $92.00 | $4.60 |
| Suma de Material | $11.58 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.045450 | $859.49 | $39.06 |
| Suma de Mano de Obra | $39.06 | ||||
| Costo Directo | $50.64 |