| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| BACE1 | ACERO DE F'C= 4200 KG/CM2 IGUAL O MAYOR | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACE1 | ACERO DE LIMITE ELASTICO IGUAL O MAYOR DE F'C=4,200 kg/cm2 | KG | 1.000000 | $9.05 | $9.05 |
| ALAM04 | ALAMBRE RECOCIDO DEL No. 18 | KG | 0.070000 | $14.50 | $1.02 |
| Suma de Material | $10.07 | ||||
| Mano de Obra | |||||
| MOM12 | OFICIAL FIERRERO | jor | 0.005000 | $187.73 | $0.94 |
| MO15 | AYUDANTE GENERAL | jor | 0.005000 | $219.18 | $1.10 |
| Suma de Mano de Obra | $2.04 | ||||
| Herramienta | |||||
| HERRAMIENTA | HERRAMIENTA MENOR | (%)mo | 0.050000 | $2.04 | $0.10 |
| EQ.SEG | EQUIPO DE SEGURIDAD | (%)mo | 0.030000 | $2.04 | $0.06 |
| Suma de Herramienta | $0.16 | ||||
| Costo Directo | $12.27 |