| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMBRACIM | cimbra en losa de cimentacion | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| E-MADERA BARROTE | MADERA DE PINO EN BARROTE DE 2" X 4" X 8' | PT | 1.500000 | $7.38 | $11.07 |
| E-MADERA TRIPLAY | TRIPLAY DE PINO DE 16 MM 1 CARA DE 1.22 X 2.44 M. | m2 | 0.250000 | $95.00 | $23.75 |
| E-MADERA POLIN | MADERA DE PINO EN POLIN DE 3 1/2 " X 3 1/2" X 8´ | pt | 0.850000 | $7.23 | $6.15 |
| 0082-05 | ALAMBRE RECOCIDO NO. 16 | kg | 0.035000 | $13.02 | $0.46 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | kg | 0.077000 | $19.03 | $1.47 |
| CIMBRA1 | Chaflan de 3/4"x 3/4" x 8' | ml | 0.200000 | $2.80 | $0.56 |
| 0950-05 | DIESEL | litro | 1.000000 | $8.93 | $8.93 |
| Suma de Material | $52.39 | ||||
| Mano de Obra | |||||
| 02-0590 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | jor | 0.129470 | $733.77 | $95.00 |
| Suma de Mano de Obra | $95.00 | ||||
| Herramienta | |||||
| 00-0001 | HERRAMIENTA MENOR | (%)mo | 0.020000 | $95.00 | $1.90 |
| 00-0002 | Equipo de seguridad | (%)mo | 0.020000 | $95.00 | $1.90 |
| Suma de Herramienta | $3.80 | ||||
| Costo Directo | $151.19 |