| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 03-2180 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA RAPIDA, AGREGADO MAXIMO 1 1/2" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.313000 | $1,298.69 | $406.49 |
| 0302-20 | ARENA | M3 | 0.462000 | $91.28 | $42.17 |
| 0302-30 | GRAVA | M3 | 0.369000 | $91.28 | $33.68 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.251000 | $2.21 | $0.55 |
| 0173-55 | FESTERMIX R.R. | CUB | 0.329400 | $202.56 | $66.72 |
| Suma de Material | $549.61 | ||||
| Mano de Obra | |||||
| 02-1030 | CUADRILLA No 103 ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.066600 | $1,630.70 | $108.60 |
| Suma de Mano de Obra | $108.60 | ||||
| Equipo | |||||
| 03-4050 | REVOLVEDORA PARA CONCRETO MIPSA-KOHLER R-10 8 H.P. 1 SACO | Hora | 0.533300 | $24.61 | $13.12 |
| Suma de Equipo | $13.12 | ||||
| Costo Directo | $671.33 |