| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 6.000000 | $16.15 | $96.90 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.100000 | $34.00 | $3.40 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.030000 | $19.00 | $0.57 |
| DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
| Suma de Material | $106.51 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.009260 | $290.45 | $2.69 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.092590 | $233.90 | $21.66 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.092590 | $181.41 | $16.80 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.046300 | $169.01 | $7.83 |
| Suma de Mano de Obra | $48.98 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $48.98 | $1.47 |
| Suma de Herramienta | $1.47 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.014810 | $200.73 | $2.97 |
| Suma de Equipo | $2.97 | ||||
| Costo Directo | $159.93 |