| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cm TAM 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS | CEMENTO GRIS | TON | 0.412000 | $1,350.00 | $556.20 |
| ARENA | ARENA | M3 | 0.535000 | $27.50 | $14.71 |
| GRAVA LIMPIA | GRAVA LIMPIA | M3 | 0.637000 | $158.60 | $101.03 |
| AGUA | AGUA | M3 | 0.243000 | $50.00 | $12.15 |
| Suma de Material | $684.09 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 40 | CUADRILLA NO. 40 (1 Operador de equipo +7 Peones) | jor | 0.066600 | $2,639.94 | $175.82 |
| Suma de Mano de Obra | $175.82 | ||||
| Equipo | |||||
| REVOLVEDORA 8 H.P. | Revolvedora Kohler sin operador. | HR | 0.533300 | $63.12 | $33.66 |
| Suma de Equipo | $33.66 | ||||
| Costo Directo | $893.57 |