| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| FCO-0100-00 | CONCRETO HECHO EN OBRA F'C=100 KG/CM2 TMA 19 MM | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAAGL001 | CEMENTO TIPO CPO 30-RS | TON | 0.273000 | $1,650.00 | $450.45 |
| MAAGRE001 | ARENA | M3 | 0.542000 | $64.29 | $34.85 |
| MAAGRE003 | GRAVA | M3 | 0.656000 | $235.00 | $154.16 |
| AGUA | AGUA | M3 | 0.271000 | $14.00 | $3.79 |
| Suma de Material | $643.25 | ||||
| Equipo | |||||
| EQREV001 | REVOLVEDORA PARA CONCRETO DE 1 SACO MOD. R-10 | HR | 0.533300 | $52.97 | $28.25 |
| Suma de Equipo | $28.25 | ||||
| Costo Directo | $671.50 |