| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ACEROA36 | ACERO ESTRUCTURAL A-36 EN PLACAS, ANGULO, O PERFIL LAMINADO DE HASTA 5.00 MTS DE ALTURA | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| E-ACERO ESTR PLACA | ACERO ESTRUCTURAL A-36 EN PLACAS, ANGULO, O PERFIL LAMINADO | KG | 1.085000 | $11.70 | $12.69 |
| E-GAS CORTES | GAS P/ CORTES | KG | 0.009000 | $8.70 | $0.08 |
| E-OXIGENO | OXIGENO | M3 | 0.013000 | $19.00 | $0.25 |
| E-SOLDADURA | SOLDADURA E 7018 | KG | 0.020000 | $45.00 | $0.90 |
| E-DISCO DESBA | DISCO DE DESBASTE DE 6" Ø | pieza | 0.002200 | $46.50 | $0.10 |
| Suma de Material | $14.02 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 OF.PAILERO + 1 AYUDANTE E. | jor | 0.002160 | $1,032.24 | $2.23 |
| 02-0770 | CUADRILLA No 77 ( 1 SOLDADOR + 1 AYUDANTE DE SOLDADOR ) | jor | 0.002550 | $895.15 | $2.28 |
| CUADRILLA N° 343 | 1 OF.MONTADOR + 4 AYUDANTE A. | jor | 0.001260 | $2,069.69 | $2.61 |
| Suma de Mano de Obra | $7.12 | ||||
| Herramienta | |||||
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)mo | 0.010000 | $7.12 | $0.07 |
| Suma de Herramienta | $0.07 | ||||
| Equipo | |||||
| 03-0021 | Equipo de corte de oxi-butano | HR | 0.013880 | $8.57 | $0.12 |
| 03-0031 | ESMERILADORA CON PLATO CUBRE ASTILLA, MODELO 1752 POTENCIA 2,000 W A 6,500, MARCA BOSCH. | hr | 0.028440 | $26.19 | $0.74 |
| 03-0029 | Soldadora Miller Mod. S64 | HR | 0.011440 | $9.51 | $0.11 |
| 03-0026 | Grua de 20 ton. | HR | 0.003681 | $454.43 | $1.67 |
| Suma de Equipo | $2.64 | ||||
| Otros | |||||
| 03-7022 | TORRE DE TRABAJO DE 0.00 A 4.00 MTS. DE ALTURA CON RUEDAS | R/D | 0.002550 | $31.52 | $0.08 |
| Suma de Otros | $0.08 | ||||
| Costo Directo | $23.93 |