| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONC.H/OF-C=150RN3/4 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS | CEMENTO GRIS | TON | 0.300000 | $1,500.00 | $450.00 |
| ARENA | Arena limpia de banco | m3 | 0.536000 | $39.00 | $20.90 |
| GRAVA 3/4" | GRAVILLA DE 3/4" | M3. | 0.400000 | $200.00 | $80.00 |
| AGUA | AGUA ACARREO EN EL INTERIOR DE LA OBRA | M3 | 0.263000 | $6.00 | $1.58 |
| Suma de Material | $552.48 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 05 | CUADRILLA NO. 5 (1 OPERADOR + 7 PEONES) | JOR | 0.030000 | $2,439.13 | $73.17 |
| Suma de Mano de Obra | $73.17 | ||||
| Equipo | |||||
| REVOLVEDORA 8 H.P. K | REVOLVEDORA JOPER-KOHLER 1 SACO 8 H.P. | M3 | 1.000000 | $27.68 | $27.68 |
| Suma de Equipo | $27.68 | ||||
| Costo Directo | $653.33 |