| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 020229 | CIMBRA APARENTE EN MURO. INCLUYE: SUMINISTRO, HABILITADO, ARMADO, COLOCACION, ACARREOS INTERNOS, COSTO POR MANO DE OBRA, MATERIALES DE CONSUMO, EQUIPO Y HERRAMIENTA. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAD003: | DUELA MADERA DE PINO 1"x4"x8' | pieza | 0.185990 | $27.00 | $5.02 |
| C3 | Polin 3 1/4"x3 1/4"x8 1/4 | pza | 0.125260 | $58.00 | $7.27 |
| MAD005: | CHAFLAN DE 1" MADERA DE PINO 8' | pieza | 0.250000 | $7.00 | $1.75 |
| CLAVO1 | CLAVO DE 2 1/2" A 3 1/2" | kg | 0.017670 | $17.84 | $0.32 |
| CLAVO | CLAVO DE 1½" | kg | 0.005240 | $24.11 | $0.13 |
| CLAVO1 | CLAVO DE 2 1/2" A 3 1/2" | kg | 0.007070 | $17.84 | $0.13 |
| DIESEL3 | Diesel | L | 0.800000 | $8.60 | $6.88 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO NO. 16 | kg | 0.091420 | $17.24 | $1.58 |
| ALAMBRON | ALAMBRON LISO DE 1/4" ( NO. 2 ) | ton | 0.001310 | $15,950.00 | $20.89 |
| VARILLA6 | VARILLA FY=4200 KG/CM2 NO. 6 ( 3/4" ) | ton | 0.000450 | $12,600.00 | $5.67 |
| Suma de Material | $49.64 | ||||
| Mano de Obra | |||||
| A02-0590 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | jor | 0.083330 | $784.69 | $65.39 |
| Suma de Mano de Obra | $65.39 | ||||
| Herramienta | |||||
| 00-0001 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $65.39 | $2.62 |
| OC-EQUIPO SEG | Equipo de Primera Seguridad (Casco, Botas, Guantes, Gafas, Chaleco Preventivo) | (%)mo | 0.040000 | $65.39 | $2.62 |
| Suma de Herramienta | $5.24 | ||||
| Otros | |||||
| BAS-MAD15 | TARIMA DE MADERA SECCION 1.22x2.44 | pieza | 0.134372 | $604.60 | $81.24 |
| Suma de Otros | $81.24 | ||||
| Costo Directo | $201.51 |