| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HERRERIA | FABRICACION Y MONTAJE DE HERRERIA (SOLO MATERIAL DE CONSUMO) | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GAS | GAS | KG | 0.009000 | $6.00 | $0.05 |
| OXIGENO | OXIGENO | M3 | 0.015700 | $25.00 | $0.39 |
| SOLDADURA E7018 | SOLDADURA E7018 | KG | 0.035000 | $30.00 | $1.05 |
| DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.002000 | $38.50 | $0.08 |
| CARDA | CARDA | PZA | 0.000350 | $195.00 | $0.07 |
| PRIMARIO EPOXICO | PRIMARIO EPOXICO | LT | 0.015000 | $60.00 | $0.90 |
| THINER | THINER | LT | 0.004500 | $9.00 | $0.04 |
| INGENIERIA | INGENIERIA | KG | 1.000000 | $0.23 | $0.23 |
| SPOT LABORATORIO | SPOT LABORATORIO | KG | 1.000000 | $0.20 | $0.20 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.035000 | $3.01 | $0.11 |
| Suma de Material | $3.12 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.001540 | $817.11 | $1.26 |
| CUADRILLA N° 342 EM | 1 of.soldador + 1 ayudante. | JOR | 0.001540 | $817.11 | $1.26 |
| CUADRILLA N° 343 EM | 1 of.montador + 4 ayudantes. | JOR | 0.001000 | $1,577.02 | $1.58 |
| CUADRILLA Nº 344 | 1 of. pintor + 2 ayudante A. | JOR | 0.000900 | $1,018.23 | $0.92 |
| Suma de Mano de Obra | $5.02 | ||||
| Equipo | |||||
| EQUIPO DE OXICORTE | Equipo de corte oxigeno-gas | HR | 0.015000 | $35.40 | $0.53 |
| SOLDADORA | Soldadora Miller Dimension Mod. 652 | HR | 0.015000 | $15.93 | $0.24 |
| ESMERILADORA | ESMERILADORA | HR | 0.050000 | $10.44 | $0.52 |
| EQUIPO DE PINTURA | Equipo de pintura marca ITSA | HR | 0.007200 | $4.77 | $0.03 |
| COMPRESOR AIRE | Compresor de aire mod. I-72212-H marca ITSA. (Incluye cable de alimentación). | HR | 0.007200 | $12.95 | $0.09 |
| GRUA | Grua de 20 ton. | HR | 0.002200 | $449.01 | $0.99 |
| Suma de Equipo | $2.40 | ||||
| Costo Directo | $10.54 |