| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| REP PAV ASF 1 | REPOSICION PAVIMENTO ASFALTICO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CARPETA ASFALTICA 1 | CARPETA ASFALTICA | M3 | 0.080000 | $1,791.80 | $143.34 |
| ASFALTO FM-1 1 | ASFALTO FM-1 | LTO | 1.500000 | $12.55 | $18.83 |
| Suma de Material | $162.17 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.007800 | $290.45 | $2.27 |
| AYUDANTE OP ESP 1 | AYUDANTE OPERARIO ESPECIALISTA | JOR | 0.015600 | $178.92 | $2.79 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.156300 | $169.01 | $26.42 |
| Suma de Mano de Obra | $31.48 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $31.48 | $0.94 |
| Suma de Herramienta | $0.94 | ||||
| Equipo | |||||
| COMPACT VIB 1 RD 1 | RODILLO VIBRATORIO DYNAPAC | HORA | 0.100000 | $253.38 | $25.34 |
| Suma de Equipo | $25.34 | ||||
| Costo Directo | $219.93 |