| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| J.C.LATERAL | JUNTA DE COLADO LATERAL | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.014300 | $7.25 | $0.10 |
| RED01 | REDONDO LISO 1" | kg | 5.980000 | $9.80 | $58.60 |
| TUBO 13 MM | POLIDUCTO DE 13 MM | ML | 3.000000 | $1.75 | $5.25 |
| SELLADOR SIKAFLEX | SIKAFLEX | CART. | 0.150000 | $58.00 | $8.70 |
| Suma de Material | $72.65 | ||||
| Mano de Obra | |||||
| CUA ALBAÑIL 2 | ( 1 ALBAÑIL + 2 PEONES ) | JOR | 0.020000 | $1,098.33 | $21.97 |
| Suma de Mano de Obra | $21.97 | ||||
| Costo Directo | $94.62 |