| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MARTELINADO | MARTELINADO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO BLANCO | CEMENTO BLANCO | Ton | 0.018000 | $3,234.00 | $58.21 |
| GRANO MARMOL | grano marmol | TON | 0.022000 | $1,510.00 | $33.22 |
| MARMOLINA. | marmolina | TON | 0.023000 | $1,600.00 | $36.80 |
| AGREGADO-002 | AGUA ACARREO INTERNO | M3 | 0.030000 | $30.00 | $0.90 |
| FESTERBOND | FESTERBOND | lt | 0.025000 | $21.85 | $0.55 |
| Suma de Material | $129.68 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | jor | 0.100000 | $756.44 | $75.64 |
| CUAD OC 01 | CUAD. 1 PEON | jor | 0.333330 | $261.31 | $87.10 |
| Suma de Mano de Obra | $162.74 | ||||
| Costo Directo | $292.42 |