| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| FCO-0250-00 | CONCRETO HECHO EN OBRA F'C=250 KG/CM2 TMA 19 MM | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAAGL001 | CEMENTO TIPO CPO 30-RS | TON | 0.412000 | $1,650.00 | $679.80 |
| MAAGRE001 | ARENA | M3 | 0.535000 | $64.29 | $34.40 |
| MAAGRE003 | GRAVA | M3 | 0.637000 | $235.00 | $149.70 |
| MAAGU001 | AGUA (MANEJO) | M3 | 0.243000 | $10.00 | $2.43 |
| Suma de Material | $866.33 | ||||
| Equipo | |||||
| EQREV001 | REVOLVEDORA PARA CONCRETO DE 1 SACO MOD. R-10 | HR | 0.533300 | $52.97 | $28.25 |
| Suma de Equipo | $28.25 | ||||
| Costo Directo | $894.58 |