| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CON200 | CONCRETO FC=200 KG/CM2 HECHO EN OBRA | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO 8 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.369800 | $1,900.00 | $702.62 |
| ARENA | ARENA | M3 | 0.532100 | $142.85 | $76.01 |
| GRAVA34 | GRAVA | M3 | 0.645200 | $198.57 | $128.12 |
| ACMXX005 | AGUA | M3 | 0.242400 | $50.00 | $12.12 |
| Suma de Material | $918.87 | ||||
| Mano de Obra | |||||
| MO5 | (1 OPERADOR DE EQUIPO + 7 PEONES) | JOR | 0.250000 | $2,638.63 | $659.66 |
| Suma de Mano de Obra | $659.66 | ||||
| Equipo | |||||
| AREVOLVEDORA | REVOLVEDORA PARA CONCRETO MARCA CIPSA MODELO R10 DE UN SACO TIPO TROMPO, CAP. 5 M3/HR, MOTOR A GASOLINA MARCA KOHLER DE 8 HP, CON REDUCTOR, MONTADA SOBRE RUEDAS TIPO B78X-13, PESO DE LA MÁQUINA CON MOTOR 363 KG. | Hora | 0.533300 | $13.69 | $7.30 |
| Suma de Equipo | $7.30 | ||||
| Costo Directo | $1,585.83 |