| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ANDAMIO-01 | ANDAMIAJE A UNA ALTURA MAXIMA DE 6 MTS. | R/D |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| COPLE P/ANDAMIO | COPLE P/ANDAMIO | R/D | 12.000000 | $1.00 | $12.00 |
| TIJERAP/ANDAMIO 155 | TIJERAP/ANDAMIO 155 | R/D | 6.000000 | $2.70 | $16.20 |
| MARCO AND. ATLAS | MARCO METALICA | R/D | 6.000000 | $3.50 | $21.00 |
| RUEDA P/ANDAMIO 6" | RUEDA P/ANDAMIO 6" | R/D | 4.000000 | $7.80 | $31.20 |
| PLATAFORMA D TRABAJO | PLATAFORMA DE TRABAJO | R/D | 2.000000 | $6.19 | $12.38 |
| FLETE ANDAMIOS | FLETE DE ANDAMIOS | viaje | 0.001500 | $650.00 | $0.98 |
| Suma de Material | $93.76 | ||||
| Otros | |||||
| BARANDAL LARGO | BARANDAL LARGO | R/D | 2.000000 | $2.40 | $4.80 |
| Suma de Otros | $4.80 | ||||
| Costo Directo | $98.56 |