| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO 150 KG/CM2 | CONCRETO DE F'C= 150KG/CM2 HECHO EN OBRA AGREGADO MAXIMO 3/4. ELABORADO CON CEMENTO CPP-30RS (RESISTENTE A LOS SULFATOS) | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO NORMAL | CEMENTO NORMAL GRIS | TON | 0.326000 | $1,704.52 | $555.67 |
| ARENA1 | ARENA PUESTA EN OBRA | m3 | 0.536000 | $48.33 | $25.90 |
| GRAVA LIMPIA | GRAVA PUESTA EN OBRA | M3 | 0.650000 | $175.71 | $114.21 |
| AGREGADO-002 | AGUA ACARREO INTERNO | M3 | 0.263000 | $40.00 | $10.52 |
| Suma de Material | $706.30 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD.2 (2 PEONES) | JOR | 0.066600 | $581.23 | $38.71 |
| Suma de Mano de Obra | $38.71 | ||||
| Equipo | |||||
| REVOLVEDORA | REVOLVEDORA 8 H.P de 1 saco | HR | 0.533300 | $49.97 | $26.65 |
| Suma de Equipo | $26.65 | ||||
| Costo Directo | $771.66 |