| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| RAMPA | RAMPA MINUSVALIDOS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.105000 | $955.28 | $100.30 |
| FIBRA FEST | FIBRA DE POLIPROPILENO PARA CONCRETO | kg | 0.090090 | $71.25 | $6.42 |
| MEMBRANA DE PARAF. | tela prs plicout | M2 | 0.300000 | $14.25 | $4.28 |
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.150000 | $5.23 | $0.78 |
| AGUA | AGUA | m3 | 0.005000 | $30.00 | $0.15 |
| MALLA ELECTROSOLDAD | malla electrosoldada 6x6-10/10 | m2 | 1.100000 | $15.74 | $17.31 |
| Suma de Material | $129.24 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-03 | (1 OFICIAL ALBAÑIL + 5 AYUDANTES). | jor | 0.025000 | $1,520.83 | $38.02 |
| Suma de Mano de Obra | $38.02 | ||||
| Equipo | |||||
| API-REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.010000 | $50.35 | $0.50 |
| API-ALLANADORA MEC | ALLANADORA MECANICA CON ASPAS | hora | 0.025000 | $88.61 | $2.22 |
| Suma de Equipo | $2.72 | ||||
| Costo Directo | $169.98 |