| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PRIMARIO ANTICORR | PRIMARIO ANTICORR Y ACABADO | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PRIMARIO ESTRUCTURAL | PRIMARIO ESTRUCTURAL | LT | 0.285700 | $42.00 | $12.00 |
| THINNER | THINNER | LT | 0.057100 | $13.10 | $0.75 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO | LT | 0.250000 | $67.00 | $16.75 |
| Suma de Material | $29.50 | ||||
| Mano de Obra | |||||
| CUAD OC PINT | ( 1 Of. Pintor + 1 Ayud.) | jor | 0.023362 | $720.08 | $16.82 |
| Suma de Mano de Obra | $16.82 | ||||
| Equipo | |||||
| EEQUIPO PINTURA | EQUIPO DE PINTURA IPSA | hora | 0.209000 | $13.03 | $2.72 |
| Suma de Equipo | $2.72 | ||||
| Costo Directo | $49.04 |