| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 020508 | CONCRETO PREMEZCLADO RESISTENCIA NORMAL VACIADO CON BOMBA F'C=250 KG/CM2 REVENIMIENTO DE 14 CM AGREGADO MAXIMO 3/4" EN COLUMNAS, TRABES Y MUROS. INCLUYE:SUMINISTRO DE MATERIALES, COSTO POR MANO DE OBRA, EQUIPO Y HERRAMIENTA. | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO4 | CONCRETO PREMEZC.RN F'C=250 KG/CM2 AGREGADO MAXIMO 3/4" | m3 | 1.030000 | $980.00 | $1,009.40 |
| CONCRETO5 | SOBRE PRECIO POR REV. 14 CM AGREG. 3/4" APTO PARABOMB.(A) | M3 | 1.030000 | $80.00 | $82.40 |
| CONCRETO | BOMBEO DE CONCRETO C/BOMBA EST. HASTA 5 NIVEL (15M ALTURA) | M3 | 0.515000 | $140.00 | $72.10 |
| CONCRETO2 | BOMBEO DE CONCRETO C/BOMBA EST. HASTA 30 M ALTURA | M3 | 0.515000 | $205.00 | $105.58 |
| Suma de Material | $1,269.48 | ||||
| Mano de Obra | |||||
| A02-1570 | CUADRILLA No. 157 (DE COLOCACION DE CONCRETO) | jor | 0.033333 | $3,530.18 | $117.66 |
| Suma de Mano de Obra | $117.66 | ||||
| Herramienta | |||||
| 00-0001 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $117.66 | $4.71 |
| OC-EQUIPO SEG | Equipo de Primera Seguridad (Casco, Botas, Guantes, Gafas, Chaleco Preventivo) | (%)mo | 0.040000 | $117.66 | $4.71 |
| Suma de Herramienta | $9.42 | ||||
| Equipo | |||||
| 0C990140-3510 | Vibrador de Concreto mot. gasolina 8 hp Kolher flecha 14 cabezal AA48 de 17/8 (45mm). | hr | 0.444400 | $43.86 | $19.49 |
| Suma de Equipo | $19.49 | ||||
| Otros | |||||
| 00-0050 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | m3 | 0.060000 | $39.90 | $2.39 |
| Suma de Otros | $2.39 | ||||
| Costo Directo | $1,418.44 |