| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 03-2080 | CONCRETO HECHO EN OBRA F'C=250 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.412000 | $1,547.80 | $637.69 |
| 0302-20 | ARENA | M3 | 0.535000 | $40.00 | $21.40 |
| 0302-30 | GRAVA | M3 | 0.637000 | $185.00 | $117.85 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.243000 | $3.14 | $0.76 |
| Suma de Material | $777.70 | ||||
| Mano de Obra | |||||
| 02-1030 | CUADRILLA No 103 ( 1 OPERADOR DE REVOLVEDORA DE 1 SACO + 7 PEONES ) | JOR | 0.066600 | $1,187.56 | $79.09 |
| Suma de Mano de Obra | $79.09 | ||||
| Costo Directo | $856.79 |