| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO-FC-300 | CONCRETO f´c= 300 Kg/cm2 | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | m3 | 0.177000 | $30.00 | $5.31 |
| ARENA | ARENA DE BANCO | m3 | 0.475000 | $160.00 | $76.00 |
| CEMENTO CPO-30RS | CEMENTO TIPO CPO-30RS, PORTLAND TIPO II MCA. MAYA | ton | 0.393000 | $2,200.00 | $864.60 |
| GRAVA | GRAVA DE 3/4" | M3 | 0.740000 | $260.00 | $192.40 |
| Suma de Material | $1,138.31 | ||||
| Mano de Obra | |||||
| CUAD.ELABORACION CO | CUADRILLA PARA ELABORACION DE MEZCLAS Y CONCRETOS | jor | 0.086957 | $2,600.78 | $226.16 |
| Suma de Mano de Obra | $226.16 | ||||
| Herramienta | |||||
| D-HERRAMIENTA MENOR | HERRAMIENTA MENOR | (%)mo | 0.030000 | $226.16 | $6.78 |
| EQUIPO DE SEGURIDAD | EQUIPO DE SEGURIDAD PERSONAL REQUERIDO DEACUERDO AL ANEXO "SI" | (%)mo | 0.030000 | $226.16 | $6.78 |
| Suma de Herramienta | $13.56 | ||||
| Equipo | |||||
| REVOL 1 SACO | REVOLVEDORA 1 SACO MCA MIPSA KHOLER DE 8 H.P. | HORA | 0.533300 | $28.74 | $15.33 |
| Suma de Equipo | $15.33 | ||||
| Costo Directo | $1,393.36 |