| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO F-C=100 H/O | Concreto hecho en obra f'c = 100 kg/cm2agregado max. 3/4" R.N. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.300000 | $1,586.70 | $476.01 |
| ARENA | ARENA | m3 | 0.542000 | $48.33 | $26.19 |
| GRAVA 3/4" | GRAVA 3/4" | M3. | 0.656000 | $186.00 | $122.02 |
| AGUA | AGUA ACARREO INTERNO | M3 | 0.325200 | $40.00 | $13.01 |
| Suma de Material | $637.23 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 40 | (1 Operador de equipo +7 Peones). | Jor | 0.055000 | $2,295.07 | $126.23 |
| Suma de Mano de Obra | $126.23 | ||||
| Costo Directo | $763.46 |