| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ANDAMIO METAL | ANDAMIO | DIA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ANDAMIO-03 | MARCO METALIC0 | PZA** | 2.000000 | $2.28 | $4.56 |
| ANDAMIO-02 | TIJERAS AND. ATLAS | PZA** | 2.000000 | $0.81 | $1.62 |
| ANDAMIO-04 | COPLE PARA ANDAMIO | PZA** | 2.000000 | $0.33 | $0.66 |
| ANDAMIO-01 | PLATAFORMA METALICA | PZA** | 0.020000 | $10.16 | $0.20 |
| Suma de Material | $7.04 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.025000 | $508.87 | $12.72 |
| Suma de Mano de Obra | $12.72 | ||||
| Costo Directo | $19.76 |